NOVEMBER GLO- CDBG- MIT Project Planning
Majority of the street work has been completed, but additional work requests are being submitted to GLO for approval to allow the contractor to complete the necessary work. The intersections of West Valley Street at South Walnut Street and West Patterson Street at North Lamar Street have experienced drainage deficiencies that require additional work.
At West Valley Street, post-construction inspections during rain events revealed ponding south of the intersection at South Walnut Street.